(Summary description)In order to solve the problems of cumbersome welding steps of the hanging device, waste materials and troublesome on-site operation, Jiuxin Mine’s Electrical and Mechanical Services decided to cut the used bolts to a length of 40cm and used 30cm waste belts to punch holes for hanging. It has been put into use when the pipeline from the mining area sump to the main sump is suspended. Compared with the original, the toughness is increased, the inconvenience of use is solved, and the cost is greatly saved. Each hanging device can save 150 yuan in material costs. Up to now, 300 hanging devices have been completed, which can save 45,000 in material costs. yuan.
Innovative hanging device for renovation of waste anchor rods in Jiuxin Mine
(Summary description)In order to solve the problems of cumbersome welding steps of the hanging device, waste materials and troublesome on-site operation, Jiuxin Mine’s Electrical and Mechanical Services decided to cut the used bolts to a length of 40cm and used 30cm waste belts to punch holes for hanging. It has been put into use when the pipeline from the mining area sump to the main sump is suspended. Compared with the original, the toughness is increased, the inconvenience of use is solved, and the cost is greatly saved. Each hanging device can save 150 yuan in material costs. Up to now, 300 hanging devices have been completed, which can save 45,000 in material costs. yuan.
- Categories:Concept innovation, management innovation, system innovation
- Author:
- Origin:
- Time of issue:2020-08-13 17:37
- Views:
In order to solve the problems of cumbersome welding steps of the hanging device, waste materials and troublesome on-site operation, Jiuxin Mine’s Electrical and Mechanical Services decided to cut the used bolts to a length of 40cm and used 30cm waste belts to punch holes for hanging. It has been put into use when the pipeline from the mining area sump to the main sump is suspended. Compared with the original, the toughness is increased, the inconvenience of use is solved, and the cost is greatly saved. Each hanging device can save 150 yuan in material costs. Up to now, 300 hanging devices have been completed, which can save 45,000 in material costs. yuan.
Scan the QR code to read on your phone
LINK
CONTACT
Add:No. 8, Youyi Road, Xincheng Community, Longgang Town,
Qinshui County, Jincheng
Group tel:0356-7069516
Email:qhnybjb@sina.com
Scan the qr codePay attention to our
All rights reserved: QINHE ENERGY GROUP CO.LTD 京ICP备xxxxxxxx号 www.300.cn